Nice documentary report on the new concourse A at ZRH. Unfortunately available in German only but nice to watch anyway...
Neues Dock A am Flughafen Zürich
Neues Dock A am Flughafen Zürich
#3
#4
Join Date: Oct 2010
Location: Switzerland
Programs: AY+ Platinum, SK Gold, BAEC Silver, airbaltic VIP, Radisson VIP
Posts: 6,531
Very interesting indeed.
Highlights:
- New Dock A will be able to handle schengen and nonschengen flights
- New Dock A will be able to handle up to 8 widebodies (Code E aircraft) on its north side
- New parking positions (5x Code C (narrowbodies)) between Dock A and B
- New taxiway allowing simultaneous operations
- Connected underground (passport control)
- Bus gates on level 0
Total increase of jetbridges will be +3:
Currently 10 on north side of Dock A, after construction 12
Currently 7 on south side of Dock A, after construction 8.
Dock B will not have Code E gates to the north anymore due to space, so will be able to accomodate 6 Code C aircraft.
Highlights:
- New Dock A will be able to handle schengen and nonschengen flights
- New Dock A will be able to handle up to 8 widebodies (Code E aircraft) on its north side
- New parking positions (5x Code C (narrowbodies)) between Dock A and B
- New taxiway allowing simultaneous operations
- Connected underground (passport control)
- Bus gates on level 0
Total increase of jetbridges will be +3:
Currently 10 on north side of Dock A, after construction 12
Currently 7 on south side of Dock A, after construction 8.
Dock B will not have Code E gates to the north anymore due to space, so will be able to accomodate 6 Code C aircraft.
#5
Join Date: Mar 2005
Location: ZRH, Switzerland
Programs: M&M, Fan of MO, Shangri-La.
Posts: 687
As nice and fascinating as this video is, the added value appears questionable to me.
$0.5 to $1 Billion just for a shiny steel and glass structure and 5 years of flying from a construction zone.
Really?
#6
Join Date: May 2009
Location: SIN (with a bit of ZRH sprinkled in)
Posts: 9,455
...and all the hardstands „H“ and „I“ (Between Dock A and Runway 28) are lost, which is a petty, because they are MUCH closer to the airside center than those dreaded ones near the maintenance base.
As nice and fascinating as this video is, the added value appears questionable to me.
$0.5 to $1 Billion just for a shiny steel and glass structure and 5 years of flying from a construction zone.
Really?
As nice and fascinating as this video is, the added value appears questionable to me.
$0.5 to $1 Billion just for a shiny steel and glass structure and 5 years of flying from a construction zone.
Really?