This website has always been accurate and updated daily if nothing else announced. But now either the authorīs died or there is a very serious problem with the A350 program:
- By a desperate delivery on New Years Eve they managed to deliver 14
planes in 2015, with continous promises of ramping up production. (Back log
is now approx 760 planes..)
- Only one plane, OH-LWD is slated for January delivery.
- That plane has only 1 test flight, while none has been delivered with less
than 4 test flights.
- Furthermore, that plane has been sitting on itīs ... in flightline since 1,5
months without a flight.
- Theoretically, AY no 5, QR no 8 and SQ no 1 could be delivered in February,
but AY 5 has only 1 test flight, on Jan 7, which is the only test flight carried
out this year. QR 8 and SQ 1 have zero...
- On top of that, there seem to be serious realiability issues with AY no 2 and
3, suggesting that 4 test flights are not enough.
Anyone has more information about this?