Originally Posted by
serfty
I initially thought that may be a possibility, but am thinking the text may relate only to the walkway above the mezzanine. The exterior part of the connector sits on the new luggage facility - I really cannot discern for sure.
A four month delay to the date as per the link in post 71 would indeed mean 2016.
Here is the original Project timeline
I think the T4 connector can open for air side connection sometime after the bus port is open - so originally May 2015 but could be as late as September?
The land side connection (i.e international arrival transfer to AA @ T4) won't be open until SSCP is ready so as early as September 2015 but as late as January 2016?