Then what are we missing?
Chris, care to elaborate a bit more? Are you saying the latest schedule calls for ALL 330's to refitted and flying by 4/2?
Let me try to explain this way.
There are three possible "states" of aircraft with regards to this refit project:
- Unmodified
- In mods
- Modified
As of today, there are 5 unmodified planes, 4 currently in mods, and 23 complete.
Chris is saying that the number of unmodified planes on 4/2 will be zero. On 4/2 (by Chris's statement), there will be zero unmodified planes, 4 in mods, and 28 completed planes. Then, a few days later, there will be 3 in mods and 29 complete, then 2 in mods and 30 complete, etc.
With approximately four aircraft completed per month, it is perfectly reasonable to conclude that the number of unmodified aircraft will be zero on 4/2.