How about 6/24-6/27 no trains....

Service Alert: Acela Express and Northeast Regional Temporary Changes Affecting Boston-New Haven-New York Service June 24 - June 27
The installation of a new bridge span on the Thames River Bridge has been rescheduled for June 24 through June 27, due to an unexpected complication encountered by Amtrak and its contractor in dismantling the bridge's counterweight.
To accommodate passengers, Amtrak is scheduling substitute rail service between Boston and New York via the inland route through Springfield, as well as other special trains that will serve segments of the Boston-New Haven-New York route. Limited connecting bus service to bypass the bridge outage will also be available during this period.