I have updated the Wiki. Here is current status according to FT'ers:
Completed:- Fin 451 | C-GITU | BHX from 2023-Apr-09 | Returned to service 2023-Oct-21 (6 months, 12 days)
- Fin 457 | C-GJWD | MLB from 2023-Oct-18 | RTS 2024-Feb-16 (3 months, 29 days)
- Fin 464* | C-FJNX | MLB from 2024-Jan-10 | RTS 2024-Apr-23 (3 months, 13 days)
- Fin 463* | C-FGKZ | MLB from 2024-Feb-16 | RTS 2024-Jun-14 (3 months, 29 days)
- Fin 452 | C-GITY | MLB from 2024-Jun-15 | RTS 2024-Aug-19 (2 months, 4 days)
- Fin 453 | C-GIUB | MLB from 2024-Aug-19 | RTS 2024-Oct-25 (2 months, 6 days)
- Fin 460* | C-GJWO | MLB from 2024-Sep-10 | RTS 2024-Dec-10 (3 months)
* These FINs appear to still have the slow ATG Wi-Fi. Others upgraded to 2Ku.
In progress:- Fin 454 | C-GIUE | MLB from 2024-Nov-5
- Fin 456 | C-GJVX | MLB from 2024-Dec-10