In the spirit of sharing what I know, one of the three 77G laggards (the 777-300ERs with the 14F 56J interiors) was meant to be going "under" for retrofit on 31/03 but hasn't so far. Reason for it are delays in 78X deliveries. The plan back in 2023 foresaw a 78X arriving in March, another two in May, one in June and another in August. The March delivery hasn't happened, and the two in May won't happen either.
just to add to this, the next -10 will probably be on site in the next 4-5 weeks, so you can extrapolate the 77W refurbish delays from that