There are some minor delay in the APM station construction that LAWA is responsible for. The big delay and why APM opening being pushed so far out is the $1billion Metro station and ITC East (yes, 1 frigging billion US dollars for an above ground metro station!) is seriously delayed beyond comprehension. The delay in the LAX Metro station also means the K line still cannot operate fully nearly 18 months after opening. It's really mind boggling but the local press have done a really poor job of reporting and holding Metro accountable for this disaster of construction planning and management.
According to an August 2023 article in the Los Angeles Business Journal, the projected “passenger service availability” date of the APM Oct. 17, 2024. The the Metro K Line may be operational as early as the fall 2024. The $1 billion figure may include the cost of the consolidated car rental facility, Metro bus plaza, bicycle parking, customer service center and passenger pick-up and drop-off area.