Originally Posted by
oliver2002
The cable was cut Tuesday evening/night and the redundancy worked till it was severely overloaded this morning with half of Frankfurt also loading the alternative as they came back to work. Companies that need IT networks to operate/exist definitely provision for redundancies. However a redundant system cannot bear the entire load especially if other orgnaisations also need it (think banking and manufacturing in the FRA area).
CS mentioned in this weeks press conference that the systems worked as designed after the cable was cut at night but next morning the IT providers software failed to distribute the load. Telekom and D Bahn are not at fault. I guess Dr Böse and co will use this statement to extract their pound of flesh at court
Während die Lufthansa damals noch erklärte hatte, das kaputte Telekom-Kabel sei für den Ausfall verantwortlich, übernahm der Konzern am Freitag nun selbst die Verantwortung für die Computer-Panne. Die Systeme seien nach dem Baggerunfall noch bis zum nächsten Morgen über Ersatzleitungen weitergelaufen, erklärte Konzernchef Carsten Spohr.
Danach hätten sich die Probleme auf Software-Ebene "hochgeschaukelt". Der IT-Dienstleister prüfe derzeit noch die Vorgänge, die vermutlich mit einer Verlagerung in die Cloud hätten vermieden werden können, sagte Spohr. Die Deutsche Bahn und die Deutsche Telekom seien nicht verantwortlich gewesen.
https://www.hessenschau.de/panorama/...lekom-100.html