FlyerTalk Forums - View Single Post - LAX Terminal Construction and Landside Access Modernization Program
Thread
:
LAX Terminal Construction and Landside Access Modernization Program
View Single Post
Aug 1, 2022 | 12:03 pm
#
139
TWA884
Moderator: Travel Safety/Security, Travel Tools, California, Los Angeles; FlyerTalk Evangelist
Join Date:
Dec 2009
Location:
LAX
Programs:
oneword Emerald
Posts:
24,796
From the
LAX August Monthly Construction and Modernization Highlights
email:
Quote:
Terminal Construction/Modernization:
Terminal 1:
A portion of the western end of the terminal on the Concourse Level is temporarily closed for the installation of a pedestrian bridge connecting the building to the APM's future Center CTA station. The airside connector bridge to Terminal 2 is temporarily closed.
Terminals 2 and 3:
Three gates are open in the new Terminal 3, with the remainder of the new concourse opening this fall. All gates are accessed through the Terminal 3 headhouse. WestJet ticketing remains in the old Terminal 2 headhouse. With the temporary closure of the connector between Terminals 1 and 2, buses to the Tom Bradley International Terminal currently depart from Gate 24.
Tom Bradley International Terminal:
A portion of the new Terminal Vertical Core is open in the north end of the building, providing new escalators and elevators to reach three levels of the terminal, as well as a route for arriving domestic passengers to access Baggage Claim 31 on the Lower/Arrivals Level. Tunnels allow access to the central entrances on both the Lower/Arrivals and Upper/Departures levels. The south entrances to the terminal, the
stairway on the south end of the building and escalators are temporarily closed.
The bike rack on the Lower/Arrivals Level at the south end of the terminal has been temporarily relocated to Parking Structure 4.
Terminals 4 and 5:
Demolition has wrapped up on the eastern half of the Terminal 4 headhouse, with work beginning on the replacement facility. Baggage claim is now located in the former Federal Inspection Station (Customs area) in the west end of the terminal. Several ticket counters have been relocated to the western portion of the ticketing lobby. Six gates in the south end of Terminal 4 are temporarily closed for the extension of the concourse.
Terminal 6:
Two new baggage claim carousels have opened as part of the Terminal Vertical Core between Terminals 5 and 6. On the Upper/Departures Level, new restrooms have opened in the core. The passenger tunnel from the Terminal 6 satellite to the baggage claim area has reopened. Several gates in the southeastern portion of the concourse are temporarily closed for renovations.
Reply
TWA884
View Public Profile
Find More Posts by TWA884
Post Options