An April 22 update on the APM to the board mentions that they now expect to complete it "in the second half of 2023" which a 3-6 month delay. This is a problem because the CONRAC (which is largely on schedule) can't open until the APM is finished.

https://lawa.granicus.com/MetaViewer...&meta_id=49677

The ITW West looks like it will open by early fall of this year, but until the APM is completed there will be bus shuttles to and from that facility.