Construction progress as at 31 October:
1) MRT Orange Line: 71.38%
2) MRT Pink Line: 66.54%
3) MRT Yellow Line: 68.31%
4) SRT Dark Red Line: 100% - S&E Installation: 86% (testing has begun)
5) BMA Gold Line: 98% - testing ongoing. Looking like a late Dec opening, perhaps 24-31 Dec?
Construction progress as at 31 December:
1) MRT Orange Line: 73.37%
2) MRT Pink Line: 70.32%
3) MRT Yellow Line: 73.26%
Other Updates:
1) BTS Silom line S4 update: this is nearly done and due to open by the end of March. The BMA has decided to change the name from Suksa Wittaya to
Saint Louis as this is a more familiar local name given the hospital, school and church near the station.
2) MRT Purple line southern extension: This tender was due out by March 2020 but it was delayed for obvious reasons. Expected to be released by the end of Feb/early March
3) MRT Brown line: final design (integrated with the N2 expressway project) should be completed by mid year and it is anticipated that this tender will be done by the end of 2021)
4) MRT Orange line western extension tender: Bids were received by the end of Sept as scheduled but then the BTSC lodged objections to the process in the Admin Court. This will hopefully be resolved in the next 2-3 months as construction was expected to begin by Jan 2021.