B) The next 2 openings will be;
1) Dec 2020 : Final section of BTS Sukhumvit line north extension to N24 Khu Khot, (Note: The next 4 stations might open earlier than this in late October)
2) Dec 2020: BMA Gold line
3) March 2021: BTS Silom line S4 station, Suksa Witthaya (now 50% complete)
3) Oct 2021: SRT Dark and Light Red lines - after a 2016 due date (though the light red line was open for 14 months back in 2013!) Don't be surprised if this is delayed until early 2022.