FlyerTalk Forums - View Single Post - Dar es Salaam Terminal 3
View Single Post
Old May 23, 2019, 5:40 am
  #11  
salehir
 
Join Date: Oct 2017
Location: UK/TZ
Programs: QRPC Plat; Marriott Plat; Hilton Gold
Posts: 354
Originally Posted by W126Pilot
There's an article in the Guardian today stating that the terminal will be "handed over" to the government on the 29th of May, with "limited testing operations" beginning July 1st, and full-scale operations beginning after that.

Considering the extensive remaining need to finish hiring staff / train staff / squawk test / certify the various systems / etc., I'd be pleased and impressed if things were fully functional by August or September.
I won't expect anything to start from the new terminal in this year... I frequent Dar airport maybe 2 or 3 times a month for domestic flights and the operations at the new airport are following the African code of work which is take it slow and easy
salehir is offline