there is more discussion in the 2 aman threads.
http://www.trustlands.com/docs/September2008bdmin.pdf
34 rooms - - approximately 900 sf each
31 luxury villas (6,000 sf each)
Hotel completion slipped from mid-2007 to mid-2008 to early 2009 and is now June 2009 (Okland Construction is now on its fourth project superintendent)
*Villas construction has not commenced. Changed architects, and project superintendent has received no word on when new plans will be completed so that construction can begin.
(from 9/11/08, pre lehman)