Kolkata New Terminal
Is there any news when this terminal is expected to open for international operations?
Dragonair has stated they will start flights to/from Hong Kong but only after the new terminal opens. |
Originally Posted by midlevels
(Post 18814701)
Is there any news when this terminal is expected to open for international operations?
Dragonair has stated they will start flights to/from Hong Kong but only after the new terminal opens. |
The last I heard was around 10/2012, which probably translates into 2013!
It is ominous that KA/CX have not loaded the new flights into their res system |
I flew through CCU this morning. Work is happening, but I can't imagine it being ready in 4 months.
Next year seems likely. Then again, I thought the Commonwealth Games would be cancelled too.... |
All you ever wanted to know is in this thread:
http://www.skyscrapercity.com/showth...12550&page=999 |
Originally Posted by SeeBuyFly
(Post 18819330)
All you ever wanted to know is in this thread:
http://www.skyscrapercity.com/showth...12550&page=999 |
There seems to be a lot of buzz that the terminal will be ready in September or October for first scheduled flights.
Dragonair's first flight from Hong Kong is scheduled to arrive on 2nd November. I wonder if it will be at the new terminal or old one. Or, possibly it will be also the inaugural flight for the new terminal? Is it realistic? |
Any news? Did the new terminal open?
|
Originally Posted by oliver2002
(Post 19937285)
Any news? Did the new terminal open?
Work on the 30-month Kolkata airport upgrade project began in January 2009 and was to be completed by June 2012 but was deferred first to August, then October, December and now January 2013. Many are apprehensive that while a formal inauguration may be done, full-fledged operations at the new terminal may be held up even longer with all airlines shifting to the new facility only by mid-2013. What has lent credence to the fears is the AAI's failure to conduct departure trials till date. Customs and Immigration departments have also not handled a live flight at the new terminal. |
So the new terminal was inaugurated Jan 20 but was only supposed to start on Jan 23 (NSCBs birthday). The pictures looked impressive, has anyone seen the inside of the new terminal yet?
|
Originally Posted by oliver2002
(Post 20244671)
So the new terminal was inaugurated Jan 20 but was only supposed to start on Jan 23 (NSCBs birthday). The pictures looked impressive, has anyone seen the inside of the new terminal yet?
My mom and relatives took an intl flight on 26th Jan ' 13 and returned on 3rd Feb'13.. Both from the old airport..:o BTW.. dragon air has already started CCU - HKG fights since Oct/Nov'12.. I guess they did not want to wait till eternity for the new terminal ops to start :rolleyes: |
On Jan 20 I was strolling about the domestic terminal killing time and saw that the new terminal seems to be connected in some way on the airside upper level. @:-)
|
Originally Posted by oliver2002
(Post 20244742)
On Jan 20 I was strolling about the domestic terminal killing time and saw that the new terminal seems to be connected in some way on the airside upper level. @:-)
|
SQ went live with the fact that they will use T2 next week:
https://twitter.com/SingaporeAir/sta...11545985519617 |
Kolkata New Terminal - User Development Fee
Here is the link for the UDF which will be charged from 1st mar'13..
http://www.jetairways.com/EN/GL/Prod...formation.aspx.. Seems to be steep IMHO.. |